WATER SYSTEM IMPROVEMENTS

LYN HAVEN FIRE DISTRICT NO. 1

LYNDONVILLE, VERMONT

Heath Construction Begins Work in Early October 2001

System water pressure was virtually non-existent during the day for the 38 users on the Lyn Haven Water system. The 30 year old 1" diameter distribution system was nearly plugged with calcium carbonate allowing only a small trickle to reach the customers.

Dufresne & Associates, PC worked with Duane Gilman, a Fire District volunteer, to define a complete replacement project for about $1.00 per day per user. Construction began in October and water service was initiated in December 2001.

KEY FEATURES

 

Leigh LaRock of

Construction Materials Testing, Inc.

Checks Compaction